NDHS replacement is still on schedule

Dave Ryan
Posted 7/17/18

Construction Schedule Phase 1: Oct. 2016-May 2017 Site work, geothermal, sports fields Phase 2: June 2017-June 2019 Building construction Phase 3: May 2019-Oct. 2019 Parking lot, bus loop; demolition …

You must be a member to read this story.

Join our family of readers for as little as $5 per month and support local, unbiased journalism.


Already a member? Log in to continue.   Otherwise, follow the link below to join.

Please log in to continue

Log in

NDHS replacement is still on schedule

Posted
Construction Schedule Phase 1: Oct. 2016-May 2017 Site work, geothermal, sports fields Phase 2: June 2017-June 2019 Building construction Phase 3: May 2019-Oct. 2019 Parking lot, bus loop; demolition of existing buildings Phase 4: August 2019-May 2020 Parking lot, site restoration
Submitted to Dorchester Banner This panoramic view from July 11 shows the progress of the North Dorchester High School Replacement Project. Submitted to Dorchester Banner
This panoramic view from July 11 shows the progress of the North Dorchester High School Replacement Project.
SHILOH – The North Dorchester High School Replacement Project has reached 60 percent of completion, Director of Operations Chris Hauge reported last week. The $43 million job is scheduled to be done in time for the beginning of the 2019 school year. The new building will replace the existing NDHS, decades old and showing its age. Work on the new site comprises not only a new building, but also a geothermal field and new sports facilities – in fact, the track was in action already this spring. “The building is virtually entirely closed in,” Mr. Hauge said in a prepared statement. “Openings either have windows and doors or temporary protection, but we are now basically weather tight.” Roof systems are nearing completion. Metal wall panels will proceed once roof work concludes. Masonry continues on the interior in the performance venue and miscellaneous column covers. Face brick will proceed in the remaining exterior areas upon completion of work in the performance venue. Other work in progress includes finishes and ceiling grid in the dining commons and other areas; ductwork is being hung; refrigerated walk-in boxes have been installed; drywall is going up; and geothermal piping work is moving rapidly, Mr. Hauge said. “This is one honkin’ big sucker for what is considered a very small high school,” Mr. Hauge said. “Still on the bubble; 0 days ahead, 0 days behind.” To see an architect’s animation of the outside and inside of the new school, visit ndhsreplacementproject.weebly.com.
featured, north-dorchester-high-school
Members and subscribers make this story possible.
You can help support non-partisan, community journalism.

x
X